Third Court Work to start mid November

Some members may have noticed that the trees have been removed from the area where the new court will be placed. Contracts between the Parish Council and the contractor, Doe Sport Ltd should be signed in the near future with the work due to start mid to November.
The work will be carried out in two phases. The first phase will be to clear the site and construct the foundations of the new court. This will be done in November/December and will not affect the existing two courts. Work will then stop during the coldest months of the winter. It will recommence, if conditions allow, in March when the tarmac will be laid and fencing will be carried out. At this stage, one court will be out of action whilst the net posts are moved and the courts are joined together. The final stage will be the painting of the new court and the moved court 2.

« »